Economy category powered by

Nexans is conducting seabed surveys between Cyprus and Crete, Energy Minister says

French company Nexans is conducting seabed surveys from Cyprus to Crete and vice versa, while it has started production of the cable that is to be used for the electricity interconnection between Cyprus and Greece.

This was revealed by Energy Minister George Papanastasiou after he was briefed by company representatives on the progress of the project to-date.

Talking to CNA after the 7 November meeting in Nicosia, Papanastasiou said that he had been briefed on the progress of the project by two Nexans representatives.

The company is constructing the cable for the Cyprus-Greece electricity interconnection as part of the Great Sea Interconnector project.

Papanastasiou said that he had been informed that the company was carrying out a seabed survey, from Cyprus to Crete and from Crete to Cyprus, with two different vessels which are currently within national territorial waters, one in Greece, the other in Cyprus, noting that according to the briefing, it is expected that the vessels will enter international waters within the coming days.

He explained that the vessels were identifying the corridors through which the two cables - approximately 15 centimetres in diameter each - will pass.

According to the Minister, the Nexans representatives also informed him that two factories, one in Norway and the other in Japan, have started production of the cables. The reason why two factories are working on the cables, he added, is to meet the schedules, which “are pressing”.

Papanastasiou noted that the project is based on the schedule agreed upon between Nexans and the implementing body, Greece’s Independent Power Transmission Operator (IPTO).

Replying to a question, he said that the contract with Nexans consists of three parts: the seabed survey, the construction of the cable, and its laying, noting that the company said that the laying of the first kilometres of the cable is expected to begin in 2026.

He added that Nexans representatives said that, unless something significant causes a change to the schedule, and if the project continues at the same pace, without being interrupted in any way, it is not expected to have any change in cost. This, however, will be assessed as the schedule progresses, he said.

(Source: CNA)

Read More

Dr Nakis Antoniou: Larnaca is standing on the cusp of transformation
Retail trade up 5.6% in both value and volume in March
Cyprus records €580.6m budget surplus in Q1 2025
Deadline for submission of income tax return for individuals on 31 July
EU report reveals Cyprus has highest share of online clothes shoppers and social media users
We enjoy a very strong relationship with Cyprus, advisor to Qatari Prime Minister says
Cyprus expects competent agency to implement GSI, Energy Minister says
Cypriots see business opportunities but fear failure, according to survey
Industrial production up 4.3% y-o-y in first two months of 2025
Tourism revenues are soaring: 35% increase to €148.9m in the first two months of 2025